JUWON VENTURES LTD.
FIELD REPORT
The experience garnered within the past five months is great
but to name a few, three aspects of structural engineering will be put into
proper perspective as highlighted and further expatiated below!
·
Fence Installation
·
Retaining Wall
·
Gate Pillars/Mounting of Gate
*AGGREGATES
Putting this into context: The essence of Aggregates cannot be overemphasized, as
it is obviously seen to be the ‘heart’ of construction either in brick-formation/brick-laying,
concretes, etc. It is therefore important for a structural engineer to uphold
standards in all stages of construction (In building and construction professionalism/integrity is often
perceived to be at stake for the handlers)
Types of
Aggregates
·
Coarse Aggregate
·
Fine Aggregate
Coarse Aggregate
Gravel mostly constitutes the coarse aggregate and the ratio
I've learned to be acceptable on sites is 1:2:4.
In this numeric expression, each figure represents different materials and the
number of head-pan(s) required. (See below illustration for further
explanation)
1 : 2
: 4
Cement Sand
Gravel
A bag of cement contains two head-pans of the content,
therefore – mixture involving one bag of cement will require four (4) head-pans
of sand and eight (8) head-pans of gravel.
Fine Aggregate
Unlike coarse aggregate where gravel/crushed-stones happened
to be a major component. In this case- Fine
Aggregates only demands cement and sand which are often used in brick-formation/brick-laying, plastering, etc
For Brick-formation
the acceptable ratio is 1:7 and 1:5 for plastering; which means for each bag of cement used, fourteen (14)
head-pans of sand will be applied and ten (10) head-pans of sand for brick-formation
and plastering respectively.
FENCE INSTALLATION
*Right of way should not be less than 5ft from access road, main road etc
·
Digging
·
Cast the base
·
Laying of bricks
·
Casting of pillars
Digging
Ø
Width = 2ft
Ø
Depth = 3ft
*Length is determined by the ‘intended’ distance to be
secured on the piece of land.
Base
Once digging is done, the application of coarse aggregate should be necessitated
to construct the base at 4inches thickness level and leave for couple days for
solidification.
Brick-formation
After digging and casting the base with coarse aggregate, it is very essential to make sure the setting out
of first-row-bricks on the concrete base must be accurate, this can be ensued
through the use of “plumb” and making sure it is horizontally proportional with
the centered line.
*In construction it is advisable to raise project a little
above standard. A good structural engineer must be cognizant of “eventualities”,
even if it appears impossible –s/he must consider the general assumption that
the primary purpose and function of a project could be abused by clients,
dwellers etc.
Therefore, the first three rows of the brick-formation
should be filled with coarse aggregate,
which would ensure fortification and enhance longevity.
Casting of pillars
In any project where the pedigree of the handler is at
stake, it is thereby important for the engineer in charge to do the needful in
ensuring a type of fence-installation that will involve the casting of
“concrete pillars” in-between its formation should be encouraged.
Along the fence formation, the measurement or distance that
separates each pillar from the other could vary. Measurement using the common
tape could reads 7ft, 8ft or even 9ft.
The size of each pillar as regards to its width and height
could be determined by different factors. Although 9inches by 9inches or 1ft by
1ft is said to be acceptable for the width while its height is determined by
the ‘intended’ space to be secured.
In other to ensure convenience for the carpentry service, a
lengthy space of 2ft could be reserved in-between the fence formation for the
construction of woodworks and casting of pillars thereon. It is also essential
to note that reinforcing bars/rebar/ironworks
give efficacy to pillars, that being said- All the woodworks constructed for
the casting of pillars between the fence-formation must be reinforced with ironworks before the application of
coarse aggregate. The reinforcing bar must be vertically positioned and centered
in each of the woodworks.
Once the pillars are cast and since solidified thereon, the
opening space between each pillar and brick formation can then be merged or
closed with bricks.
RETAINING WALL
Amongst many functions of retaining wall, it controls erosion especially soil erosion and
prevents mud or small rivulets on a slope from pouring down.
In this situation `I mean focusing on its purpose on site’
a concrete wall is cast using coarse aggregate mainly to stop the pouring down
of erosion from a sloppy topography.
·
Digging
·
Reinforcing bar (Rebar)/Ironwork
·
Cast the base
·
Bracing
·
Cast the wall
Digging
Ø
Width = 3ft
Ø
Depth = 3ft
*Length is determined by the intended distance to be secured
on the piece of land.
Reinforcing Bar
(Rebar)/Ironwork
In this type of construction, reinforcing bars are in two
patterns. The positioning of the ironworks are both in horizontal and vertical
forms; the concrete base will submerged the former, while the latter will be
buried in the wall. Reinforcing bars are considered to be the `heart and soul’
of retaining wall, it strengthens
the wall and gives it power to withstand pressure!
Cast the base
The next process will involved the application of coarse
aggregate at 6inches thickness level, which will successfully engulfed the 2ft
–wide rebar lying inside the pit in a horizontal position.
Bracing
There are different types of bracing designs; we have steal
design, concrete design etc.
*Using concrete design –reference to field report!
A 2ft –wide plank is placed on the far edge of the concrete base and tilted toward the reinforcing bar in standing position, I
mean the vertical ironwork intended to be buried inside the main wall.
Measuring the space between the top of the *tilted plank and the standing rebar
should be 3inches or thereabout and a carpentry service must be initiated to
maintain the needed measurement, as well as accommodating the use of poker vibrator.
The next process would
be to apply coarse aggregate all the way from the top of the 2ft –*tilted plank
down to the far corner of the base. The use of poker vibrator must be encouraged to ensure fortification and
solidification
Cast the wall
In all the processes involved in constructing A Retaining Wall, it is important for
the handler to uphold standards in all its stages. Expertise generally say
there won't be a second chance for a structural engineer to get it right;
s/he can only get it right once!
As soon as the concrete bracing solidifies, carpentry
service will follow suit to prepare a mold-box/frame from the bracing all the
way up until the vertical reinforcing bars are equaled and the intended height
is accomplished. Thereafter, coarse aggregate could then be applied and leave for
couple days to solidify.
GATE
PILLARS/MOUNTING OF GATE
Literally –Gates give access to a secured piece of land.
·
Digging
·
Placement of Rebar/Reinforcing bar/Ironwork
·
Cast the
base
·
Mount the gates
·
Carpentry Service
·
Cast the pillars
Digging
Ø
Width = 3ft
Ø
Depth = 3ft
After acknowledging the size and measurement of the gate
intending to mount; the job of the handler is made easy by knowing the distance
between both pillars and to identify the two spots where digging will commence.
Two separate spot will be dug; the digging measurements for
both pits are 3ft deep and 3ft wide on four sides.
Placement of
Rebar/Reinforcing bar/Ironwork
The reinforcing bars are in two forms; the horizontal rebar
which is known as mat and the
vertical rebar. The mat will be buried
inside the concrete base while the gate-pillars will swallow the vertical
reinforcing bar.
The type of steel for the rebar will be determined by the
size of the gate-pillars, the bigger the pillar the bigger the reinforcing bar.
A pillar of 1ft by 1ft is welcome to use 12mm steel for both the mat and the
vertical rebar.
Note
The vertical measurement of the reinforcing bar is
determined by the height of the gate, which in-turn will be the height of the
pillar and presumably the height of the fence.
Thereafter, the vertical rebar will be centered on the horizontal
rebar (mat) with the aid of binding wire and this process must be checked with
continuous use of plumb for accuracy and ensure an upright positioning.
Also the positioning of both pillars must be linear to the
fence installation and this can be achieved through the conventional use of line/rope
to align the vertical reinforcing bars with the fence.
Cast the base
Thereafter – both pits will be filled with coarse aggregate.
This process will submerge the mat on
2ft by 2ft and a thickness level of 9inches which apparently will
engulf a portion of the vertical rebar.
Mount the gates
It is not advisable to introduce the gates before the
concrete-base in both pits solidifies. By extension, a day or two could be
dedicated for the aggregate to bake. Thenceforth, the gates would be mounted
and married together with the vertical rebar on both sides. Once the gates are
accurately positioned with the aid of plumb, it can then be tightened
with binding wire to steadfastly hold it together with the vertical reinforcing
bars and maintain the accuracy.
Carpentry Service
The construction of woodwork will commence from the
concrete-base: Using planks –A 1ft by 1ft vertical mold-box/four-sides
frame will be fastened together and strong enough to accommodate the use of poker vibrator, therefore suspending
the vertical reinforcing bar married with a portion of the gate in its middle.
This should be carried out on both sides.
Cast the pillars
The next stage would be the introduction of coarse aggregate
to fill up both frameworks/mold-boxes.
Note
In other to ensure the pillars are firmly baked –a poker
vibrator should be introduced at every 4m of the filling process, I mean
during application of coarse aggregate.











No comments:
Post a Comment